Processing Shed – Update 2

Work is progressing well.  Last week the internal cementing was completed.  The guys did a great job.  With the hot weather matting was applied to the wet concrete to reduce the risk of cracking and it worked like a treat.  The finished product is fantastic – no cracks.

This week the external cladding was completed and next week the internal services such as water, gas and electricity will be connected before we start internal cladding.